Guide

A checklist for a RICS Level 2 inspection

A practical before, during and after checklist for a RICS Home Survey Level 2 inspection, following the order of the Level 2 report.

Updated

The short answer

Before the visit, confirm terms of engagement, do your desk-top research and check your equipment. On site, work through the property in the order of the report: outside, inside, services and grounds, noting limitations and taking photos. Afterwards, rate each element, list issues for the legal advisers and risks, write the overall opinion and check the report before you sign it.

This checklist follows the order of the RICS Home Survey Level 2 report, so your notes line up with the report as you work. Adapt it to your own procedures and to the property in front of you. It's a prompt, not a substitute for the standard or your professional judgement.

Before the visit

  • Terms of engagement agreed and signed, with the level of service and any extras (such as a valuation) clear
  • Client's concerns and plans noted, for example extensions or known issues
  • Access arranged with the agent or vendor, including keys, alarms and any pets
  • Desk-top research done: maps, flood risk, planning history, listed building or conservation area status, mining or ground issues where relevant
  • Property type and likely construction checked, and your competence for it confirmed
  • Equipment packed and working: damp meter, torch, binoculars, ladder, camera or phone, tape or laser measure, spare batteries
  • Lone working and safety arrangements in place
  • Phone charged, and your app or forms ready for offline use if signal is likely to be poor

On arrival

  • Note the date, time, weather and recent weather (it affects damp readings and roofs)
  • Note whether the property is occupied, furnished or empty
  • Note anything restricting the inspection, such as stored goods, fitted floor coverings or locked rooms
  • Take a front elevation photo and a general view of the street

About the property

  • Type of property, approximate age and construction
  • Accommodation: floors, rooms and their layout
  • Any extensions, conversions or alterations, with an approximate date if you can tell
  • Energy efficiency information you can see or check
  • Location and facilities, and anything nearby that may affect the property

Outside the property

The elements in section D of the Level 2 report:

  • D1 Chimney stacks: condition of brickwork, pointing, flashings and pots
  • D2 Roof coverings: type, slipped or missing coverings, ridges, valleys, flat roofs
  • D3 Rainwater pipes and gutters: leaks, blockages, falls, discharge points
  • D4 Main walls: construction, cracking, bulging, pointing, render, damp proof course, ground levels, air bricks
  • D5 Windows: type, condition, operation, sills
  • D6 Outside doors (including patio doors): condition and security
  • D7 Conservatory and porches: construction, condition, roof
  • D8 Other joinery and finishes: fascias, soffits, bargeboards, decoration
  • D9 Other: anything else on the outside

For each, record what you saw, from where, and any limitations, such as parts hidden from view.

Inside the property

The elements in section E:

  • E1 Roof structure: enter the roof space where safe; timbers, insulation, ventilation, signs of leaks or pests
  • E2 Ceilings: cracking, staining, sagging
  • E3 Walls and partitions: cracking, damp readings, removed walls
  • E4 Floors: deflection, springiness, ventilation under suspended floors
  • E5 Fireplaces, chimney breasts and flues: condition, removed breasts, ventilation
  • E6 Built-in fittings: kitchen and other fittings, not appliances
  • E7 Woodwork: staircase, doors, skirtings
  • E8 Bathroom fittings: sanitary ware, seals, extraction
  • E9 Other: anything else inside, such as basements or cellars

Services

Services are inspected visually only, without specialist tests. Record what you can see and recommend testing by a qualified person where appropriate.

  • F1 Electricity: consumer unit, visible wiring, any test certificates
  • F2 Gas/oil: meter, supply, tank and its location
  • F3 Water: stopcock, visible pipework, water tanks
  • F4 Heating: boiler or heat source, age, flue, service records
  • F5 Water heating: cylinder or combination system
  • F6 Drainage: note the system type and look at inspection chambers where it's safe and your terms allow
  • F7 Common services: for flats, shared services you can see

Grounds

  • G1 Garage: construction, roof, doors, condition
  • G2 Permanent outbuildings and other structures: sheds, summer houses, retaining walls
  • G3 Other: boundaries, paths, drives, trees near the building, shared areas

Issues for the legal advisers

  • Regulation: alterations or extensions that may need planning permission or building regulations approval
  • Guarantees: damp proofing, timber treatment, windows, roofing, cavity wall insulation, solar panels
  • Other matters: rights of way, shared drives, boundaries, leases and service charges for flats

Risks

  • Risks to the building, such as movement, damp, timber defects or nearby trees
  • Risks to the grounds, such as flooding or invasive plants
  • Risks to people, such as suspected asbestos, unsafe glazing or a lack of smoke alarms
  • Other risks or hazards

Before you leave

  • Every element has notes and photos, or a reason it couldn't be inspected
  • Limitations are recorded for each section
  • Notes and photos are saved, or set to sync when you have signal
  • Anything you moved is put back and the property is secure

Writing up

  • Give each element a condition rating, or NI with a reason (see condition ratings explained)
  • Make sure every 3 has a clear explanation and next step
  • Recommend further investigation where you can't reach a conclusion, with who should do it
  • Write the overall opinion last, and check it matches the ratings
  • Complete the issues for legal advisers and risks sections
  • Add the valuation, if it was part of the instruction
  • Check names, address, dates and photos, then sign the surveyor's declaration

Element names above follow the RICS Level 2 report template. Always work from the current template and the RICS Home Survey Standard.

In PropScribe, a Level 2 survey opens with these same sections and elements ready to fill in on your phone, so your notes and photos land in the right place as you go. You then review the AI first draft and sign it off. See features. PropScribe is not affiliated with or endorsed by RICS.

Try it on your next survey.

Capture on site, get a first draft, then review and sign it off yourself.

Start free trial See how it works

Free for 7 days, then £39.99 a month if you upgrade. No card needed.